Hoisting and installation of wall color steel panel?
1. Wall color steel plate can be hoisted manually by pulley.
2. The base line of the wall panel installation can be determined according to the relative position of the steel structure or the method of hanging the wire with the theodolite wire hammer.
3. The wall panel should be installed in order from top to bottom, and be fixed while lifting.
4. The angled floodboard should be processed and installed according to the measured dimensions after the wallboard is installed.
5. For each installation of 3 to 5 wall panels, the verticality of the board should be checked once to eliminate the vertical deviation of the board in time.
6. The self-tapping bolts and other connecting parts of the wallboard are perpendicular to the board, and should not be too tight or too loose. Its strength should be the same as the gasket after extrusion